Boeing initially was set up to provide the Dreamliner to airline company consumers in mid-2008. After 5 revealed hold-ups over 2 years, the business was compelled to delay the very first test air travel. One motorist for the hold-up was an industry-wide lack of aerospace fasteners, the hardware that held the airplane together.
Engineers at Boeing never ever might have envisioned that fasteners, which consist of roughly 3% of the overall expense of an airplane, would end up being such a problem. To deal with the fastener concern, Boeing's management understood that it might not simply utilize a band-aid option; rather, it needed to drive sweeping modifications to the method the market and supply chain worked. Boeing's option: the fastener procurement design (FPM).